Posted on May 26, 2021 at 10:07 AM by Maggie Le
The Magnolia Street Bridge has been open on the morning of May 22. There will continue to be lane closures on Magnolia Street between Warner and Heil for median work between May 22 and June 1. The new bridge will have 2 additional travel lanes and bike lanes in each direction.
Shortly following the opening of Magnolia Street Bridge, Warner Avenue Bridge will be closed to vehicle and pedestrian traffic in preparation for demolition and reconstruction. Currently crews have been preparing Warner Avenue area for the demolition. Demolition will occur during 3 consecutive weekend for freeway full closures in June.
For information on detours, closures, major construction activities, full freeway closures, and bridge demolitions please visit www.octa.net/405improvement or contact the 405 Community Outreach Team at (888)400-8994 or 405project@octa.net.