Fountain Valley Recreation Center Park Expansion

  
 
 
 

 
 
RECREATION CENTER BUILDING REHABILITATION

August 31, 2007 — The rehabilitation of the Recreation Center Building is on schedule.  Interior painting will be completed by Friday, August 31, new ceiling tiles should be installed Wednesday, September 5, and the new flooring completed by Friday, September 7. The following week will be utilized for final touch up work, addressing punch list items, clean up and returning of furniture and other movable items to their original locations. As scheduled, the building will be complete, open, and available to the public on September 17.

 

 

 

 

 

<< Older                                                                        Newer >>


 

City of Fountain Valley, 10200 Slater Avenue, Fountain Valley, CA 92708
 Phone: (714)593-4400 Fax: (714) 593-4494 Email: fvproud@fountainvalley.org
 Privacy Policy | Site Map | Usage Policy